How to make an adjudication application in Victoria

Victorian security of payment deadlines, the notice required when no schedule arrives, evidence for an application and how to serve it.

Does Victorian adjudication cover the job?

If a builder has reduced your progress claim, the date you received its payment schedule can start the adjudication clock even while payment is still weeks away. If the builder stayed silent, the payment due date and a further notice control when you can apply. Establish which happened before calculating your deadline under section 18 of the Building and Construction Industry Security of Payment Act 2002 (Vic).

The Act covers construction work in Victoria and related goods and services, including plant hire, engineering and quantity surveying. It can apply to an oral subcontract. A builder’s domestic building contract with a private homeowner is generally excluded. A subcontractor engaged by the builder on the same house can still qualify. Identify the party that engaged you and the work covered by your own agreement (ss 5–7, 9(1)).

The rules below cover progress payment claims served on or after 15 April 2026, including under earlier contracts. Earlier claims and adjudication applications already pending at commencement generally retain the former Part 3 procedure. The current service rules apply to documents required to be served, given or lodged from commencement (s 54(1)–(3), (6)–(9)). A claim to release performance security follows a separate procedure under section 18A.

Check the claim, the schedule and the payment due date

A payment claim identifies the work or supply, specifies the amount claimed and states that it is made under the Victorian Act (s 14(2)). For a progress claim, show the work period, quantities or milestones, rates, prior payments and balance. That lets the respondent check each amount against the job records.

You can ordinarily claim from the last day of a month in which you performed work or supplied goods or services. An earlier contractual date can apply. For work or supply from 1 to 21 December, the statutory date is 22 December. For 22 to 31 December, it is 31 January of the following year. An early claim takes effect on the first permitted day. Ordinarily only one claim may be served per month unless the contract provides otherwise (ss 14A(1)–(5), 14D(1)).

At the end of a project, the final day for service is the day before the latest applicable date under section 14C. Compare the contractual last date for service, six months after practical completion of all contracted work, and six months after all contracted goods and services were supplied.

Record two dates separately. The schedule is due by the earlier of the contractual deadline and 10 business days after service (s 15(4)). Payment falls due under the contract, subject to a maximum of 20 business days after service. Without an express payment date, payment is due 10 business days after the earliest permitted claim date (s 12(1), (1B)). Serving the claim later can make those two deadlines quite different.

Which adjudication deadline applies?

  • The schedule allows less than you claimed. Lodge within 10 business days after you receive the schedule. The right to challenge the reduction arises on receipt, including where the respondent schedules zero (s 18(1)(a)(i), (3)(c)).
  • The respondent scheduled an amount but failed to pay all of it on time. Lodge within 10 business days after the payment due date. If you also dispute a reduction, record the separate deadline that started on receipt of the schedule (s 18(1)(a)(i)–(ii), (3)(c)–(d)).
  • No timely schedule and part or all of the claim remains unpaid at the due date. Within 10 business days after that due date, serve notice of your intention to seek adjudication. The notice must tell the respondent it may serve a payment schedule within five business days after receiving the notice. Once those five business days expire, lodge within the next five business days. A schedule served in response belongs in the application and does not restart that clock (s 18(1)(b), (2), (2A), (3)(e)–(f)).

Count from the business day after the triggering event. Omit Saturdays, Sundays, days observed throughout Victoria as a full or part-day public holiday, and the period from 22 December to 10 January inclusive (s 4(1), definition of business day).

Example of a claim that received no schedule

A commercial subcontractor served its July claim on Friday 31 July 2026. Assume that was the earliest permitted date, the contract set neither a payment date nor a shorter schedule period, and no payment or schedule arrived. Payment was due Friday 14 August. The builder received the section 18(2) notice on Monday 17 August. Its five business days ended on Monday 24 August. The subcontractor could lodge from Tuesday 25 August through Monday 31 August. If it lodged on Wednesday 26 August, its copy had to reach the builder by valid service no later than Monday 31 August (ss 12(1)(b), 15(4), 18(2)–(5)).

What belongs in the adjudication application?

Identify the payment claim and any schedule, state the amount you seek and explain the difference between the parties’ figures. Start with the contract, amendments, claim and attachments exactly as served, schedule, any section 18(2) notice, and evidence of when each document was received. A dated chronology connects those records to the particular deadline under section 18.

For each disputed item, identify the contract clause or instruction, the work done, its value, the respondent’s reason for withholding and the document that answers it. If the dispute is over extra excavation, a written direction establishes what changed, surveyed levels or signed dockets establish how much was excavated, and the relevant rate establishes its value. Show the arithmetic and deduct payments already received. The 2026 reforms removed the former restrictions on claimable variations and excluded amounts. The basis and value of each item still have to be established (ss 10(1), 11(1)–(2), 23(2), (2A)).

Where to lodge and how to serve the respondent

Lodge the written application with a Victorian authorised nominating authority and include any application fee it charges. If the contract lists three or more authorised nominating authorities, choose one on that list. Otherwise, choose one from the Building and Plumbing Commission’s register (s 18(3)(a)–(b), (f)–(h), (4)).

Serve the respondent with the complete application, including its attachments, within three business days after lodgement (s 18(5)). Under section 50, use the contractual service method if reasonably practicable. Otherwise use an available statutory method. If relying on an agreed portal or email address, keep the instruction authorising that method and evidence of receipt. Lodgement with the authority and service on the respondent each need their own record.

What happens after the decision?

If the adjudicator awards a payment, the respondent must pay within five business days after it is given the determination, unless the adjudicator sets a later date (s 28M(1)–(2)). If the amount remains unpaid, the claimant can obtain an adjudication certificate from the nominating authority and file it in a court of competent jurisdiction with an affidavit identifying the unpaid amount (ss 28O(1), 28Q, 28R(1)–(2)).

Victorian legislation, forms and authorities

Updated 20 November 2026.

Melbourne contact address

Adjudication Lawyers Pty Ltd trading as Adjudicate Now

Level 14, 333 Collins Street
Melbourne VIC 3000

03 8618 6803

Contact us to arrange a meeting. View Melbourne contact details →

Discuss your payment claim.

Provide the project location, the amount outstanding and the dates of any payment claim or schedule.

Discuss your claim →