Answering a defect backcharge in adjudication

When a payment schedule deducts rectification costs, first establish what the deduction represents. The respondent may have reduced the value of incomplete or defective work, claimed the cost of a third party’s repair, or applied both adjustments. Those calculations answer different questions and can overlap.

Identify the work and the contractual basis

Set out the location, drawing detail, specification requirement and the particular departure alleged. Check who carried out that part of the work and what happened after handover to another trade. Where the deduction relies on a rectification or set-off clause, identify the term and the steps the respondent says it followed. Include the notice, your response and any inspection report bearing on responsibility.

Examine the repair cost

Follow the deduction through the repair scope, quotation, instruction, invoice and any record of payment that exists. A quotation may support an estimate. An invoice may show what was charged. Read the work description on each. A contractor repairing an industrial floor may mobilise once to address several trades’ work. Check what share of that mobilisation has been attributed to your package and the basis for the allocation.

Give a reasoned figure for the item

Compare the defect deduction with the value already withheld against the same location. If the schedule removes the full value of the original work and also charges for replacement, identify the overlap and explain the valuation you contend follows from the contract. Where part of a repair genuinely concerns a different area, isolate it. Finish with the amount claimed, the amount scheduled, the adjustment supported by the evidence and the resulting difference. A bare rejection of the invoice gives the adjudicator little assistance in deciding that difference.

Worked example — a repair invoice with three different jobs

Suppose a Queensland contractor claims $68,000 for an installed drainage package. The payment schedule deducts a $14,400 invoice from another tradesperson. The invoice covers $6,000 to repair four damaged joints, $5,400 to redesign a separate outlet and $3,000 to reinstate landscaping. The schedule describes the whole sum as rectification. The claim is then valued at $53,600. Treating the invoice as one indivisible expense conceals three quite different questions.

Find the inspection records for the four joints and locate each on the as-built drawing. Compare the observed condition with the specified seal or installation tolerance. Determine what repair was needed and check whether the tradesperson's quantity and rate match the necessary work. For the outlet, compare the installed design with the drawing issued for construction. If the principal chose a larger outlet for operational reasons, establish that change separately. A design improvement does not become repair of defective work merely because the same crew carried out both tasks on the same day.

Trace the landscaping item to the excavation used for the joint repairs. Suppose the records show that half the reinstatement related to the joint repairs and half to the redesign. On the assumption that the contractor bears the reasonable repair costs and the claimed rates are established, $6,000 plus $1,500 gives $7,500. The resulting value is $60,500 before other adjustments on the same tax basis. The difference from the scheduled value is $6,900. State the assumptions alongside the figure so a different finding on the landscaping changes only that part of the calculation.

Queensland valuation and contractual deductions

Section 72(1)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) applies the contract's valuation provisions where they cover the matter. If the contract does not provide for it, section 72(1)(b)(iv) identifies the estimated cost of rectifying defective work as a valuation consideration. Distinguish that exercise from a separate contractual backcharge. For a backcharge, identify the term permitting it and any applicable notice or opportunity to rectify. The estimate used to value work and the amount the principal actually spent may differ.

Read the original defect notice, the contractor's reply and any record of access. A notice may identify four joints while the repairer replaced twelve as a precaution. Establish why replacement of the extra eight was needed. A photograph taken after replacement will show the finished result but may tell the reader little about the original condition. Before-and-after photographs with dates, locations and an explanation from the person who inspected the work are more informative.

Follow the money through the schedule

Compare the deduction with any reduction already made to the original progress item. The schedule might value all the drainage at 90% because of the defects and also deduct the full cost of repairing them. Establish what the percentage reduction represents. If it prices incomplete work in another area, both adjustments may need examination. If it already accounts for the same four joints, identify the duplicated allowance explicitly.

Order the exhibits around location, contractual requirement, departure, repair and price. Separate labour, materials, access, plant and reinstatement where the invoice permits. Where it does not, ask for the underlying timesheets or estimate and explain any allocation you make. End with the accepted repair cost, each contested item and the net payment sought. That gives the adjudicator a workable figure even if the evidence supports a different allocation of one expense.