When a payment schedule accepts the quantity but substitutes a lower rate, the dispute has narrowed. Begin the adjudication submission with the two rates, the quantity accepted and the amount attributable to the difference. Then explain what each rate buys under the contract.
Read beyond the rate description
On a civil works package, a rate for loading excavated material may look close to a rate for removing spoil. Look at the schedule preamble, haul distance, disposal destination, unit of measurement and responsibility for tip fees. An hourly plant rate can include an operator and fuel. A separately listed operator or fuel charge needs an explanation. Name the particular inclusion or omission that makes the respondent's proposed rate applicable or unsuitable.
Follow the agreed pricing sequence
Find the variation valuation clause. It may direct the parties to use an existing rate, adapt a comparable rate or build a new price where the existing rates do not fit. Follow the sequence the parties agreed. If you adapt a rate, identify the component retained and the component adjusted. For an additional haul, show how distance, cycle time and vehicle capacity affect the price. Give the adjudicator the source of each input.
Show the effect on the claim
Apply the rival rates to the same measured quantity, on the same tax basis, and deduct the amount already allowed for that item. If the respondent also disputes the quantity, calculate that difference separately. An adjudicator who accepts the measurement but takes a different view of one component of the rate should be able to calculate the resulting amount from the exhibit.
Worked example — one activity, two rate descriptions
Assume a Queensland civil subcontract has an agreed rate of $88 per metre for open trench in ordinary ground and $156 per metre for trench excavated in classified rock. A payment claim applies the rock rate to all 230 metres in reach C. The schedule applies the ordinary rate throughout. The difference is $15,640. Before debating the rates themselves, decide what the two descriptions mean and over what distances the actual conditions satisfy them.
Read the contract definition of rock. The example assumes classification depends on a specified excavation method and an agreed record at the face. The geotechnical report predicts a rock band, but a prediction cannot establish its start and finish. Locate the chainages in the foreman's reports, excavator attachments log and joint inspections. Suppose the contemporaneous records support rock from chainage 40 to chainage 130, a length of 90 metres. That leaves 140 metres of ordinary trench.
The supported valuation is 90 times $156 plus 140 times $88, giving $26,360 before GST. The scheduled valuation is $20,240. The difference on these assumptions is $6,120. Compare that calculation with the $35,880 originally claimed and identify the $9,520 reduction. Showing the original figure, the scheduled figure and the amount supported by the records makes the remaining disagreement visible. It also avoids presenting the revised calculation as a different stretch of work.
Read the inclusions before comparing prices
Under section 72(1)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), the contractual valuation governs where it covers the matter. Section 72(1)(b) gives the considerations where the contract does not provide for valuation. A schedule of rates can answer how much is payable without answering which item fits. Read the unit, description, qualifications and measurement notes as a set. A heading on the first page may apply to several items listed on the next.
Check whether either trench rate includes loading, haulage, disposal, bedding or dewatering. If both include disposal to a nominated site, a comparison with a third-party excavation quotation excluding transport will misstate the price difference. Where the instruction changes the disposal location, identify the changed operation and deal with its valuation separately. The higher rock rate cannot automatically carry every additional cost encountered along the reach.
Make disputed classification reproducible
Use a plan marked with start and end chainages. A second line on the plan can show where the respondent agrees rock occurred, where it disagrees and where the records are incomplete. Attach photographs with a scale and a link to the corresponding shift report. If inspection was interrupted, explain which boundary is measured and which is estimated. Quantify the effect of moving the estimated boundary by five metres. At a rate difference of $68 per metre that one adjustment changes the comparison by $340.
Then check whether the disputed lengths were already certified in an earlier claim. A cumulative valuation may include several reaches while the outstanding dispute concerns only reach C. Reconcile the earlier payments by reach and rate, retain a common tax basis and explain any rounding. End with a table that can be read without the spreadsheet: contract item, accepted quantity, disputed quantity, adopted rate and extension. The adjudicator can then accept a different rock boundary without having to guess the rest of the calculation.
Where classification turns on equipment capability, identify the machine model, fitted attachment and operating conditions for the shift. A photograph of a breaker parked beside the trench can establish its presence while leaving open whether the crew used it on the disputed length. The shift report helps resolve that question.