Proving delay behind a payment item in adjudication

A diary can prove that access was late. It takes a further step to show whether the lost access delayed a contractual milestone, which costs followed and why the contract makes those costs payable. All three questions matter when delay forms part of a payment claim.

Identify what the work was waiting for

Take the commissioning of an industrial switchboard. The room, permanent power and testing crew may all have to be available before commissioning starts. Identify the planned access date, the work then ready to begin and the record of when access was available. Use the programme update immediately before the event. An original tender programme may no longer represent the sequence the team was following.

Test what controlled completion

Trace the affected activity to its successors and the relevant milestone. Check available float and whether another unfinished activity independently held up testing. Compare the planned sequence against actual access records, energisation records, shift logs and the next programme update. If the crew moved to another work front, identify the period absorbed by that move and the period for which the claimed effect remained.

Connect the period to the money

Identify the clause relied on for payment, any notice required and the pricing method. A granted extension answers a question about time. Read the separate provisions dealing with compensation before attaching a daily amount. If the claim is for actual site costs, match personnel and plant to the affected period and account for any use elsewhere. If the contract provides a daily rate, identify its conditions and apply it to the supported days. The final calculation should distinguish the days lost on the programme from the days priced in the claim.

Worked example — eight days on site and three days to completion

Suppose a New South Wales process project has an accepted programme showing that pump installation must finish before pressure testing starts. Access to the pump area is withheld for eight working days. The programme immediately before the restriction shows five working days of float on that path. The contractor claims eight days of site overhead at $2,100 per day. The superintendent says another crew was working elsewhere throughout that period and allows nothing.

Begin with the programme data date. Check actual progress up to that date and identify whether installation still had five days of float when access was lost. On the simple assumption of no other changes and an unchanged controlling path, eight days of lost access consume five days of float and move completion by three working days. That is a time result, before considering entitlement or cost. Work continuing elsewhere is consistent with a delay to completion if the remaining activities cannot bring the relevant milestone forward.

Now turn to the payment claim. Assume the contract permits recovery of proven additional time-related costs caused by this event and the records substantiate $2,100 a day for the three extra days at completion. The extension of site overhead on that basis is $6,300, against $16,800 claimed. A crew genuinely stood down earlier might have a separate cost even while float was available. Identify the contractual basis, dates and actual resources for that amount. Adding crew standby to site overhead requires a check that the same labour does not appear in both.

The claim needs both a time result and a payment basis

Section 9(a) of the Building and Construction Industry Security of Payment Act 1999 (NSW) directs calculation of the progress payment by the contract where it provides for the matter. Section 22(2)(b) and (c) makes the contract and duly made supporting material relevant to adjudication. An extension-of-time clause and a compensable-delay clause may address different events or impose different conditions. Identify the obligation relied on for money and show which steps the project team took to satisfy it.

Test the result against the next programme update and the eventual commissioning records. A later delay to electrical energisation may have become controlling. Mark when it arose and which activities it affected. Avoid attributing the later period to the withheld pump access merely because both events occurred before the completion certificate. Where alternative logic links produce a different finish date, show the competing links and explain which matches the sequence actually available on site.

Present a chronology that survives checking

Include the accepted programme, the last reliable update before the event, the direction restricting access and the record restoring it. Add dated progress information for installation and testing. A short extract of the affected path should identify predecessors, successors, calendars and any constraints. Supply a readable print as well as the supporting programme data where available. A bar ending later on a coloured chart gives no indication whether a changed link or a real event moved it.

For costs, show how the claimed daily amount was built up and what expenses genuinely continued. A site manager assigned to another project immediately after the original finish cannot automatically remain in the extension calculation. A hired site shed retained specifically for commissioning may have an invoice covering the additional period. Reconcile the cost dates with the time analysis and with sums already claimed as preliminaries. The final presentation should allow the adjudicator to decide time, responsibility and money separately.