Separating acceleration costs from ordinary labour in adjudication

Putting a second crew on a work front increases expenditure. Whether that expenditure supports the amount in a payment claim depends on the contract, why the extra crew was engaged and how much of its work was already included in the original price.

Establish the change in working arrangements

Identify the instruction, agreement or contract provision relied on. Set out the required completion date and the programme the contractor was following immediately beforehand. For a piping package moved to double shifts, preserve the look-ahead programme, planned crew size, shift roster and correspondence agreeing to the change. Explain whether the direction brought forward a milestone, changed the sequence or required recovery of a particular delay. Identify what the parties agreed about price.

Price the difference

Compare ordinary hours and resources already allowed against what changed. A payroll report may contain the full wages of a night crew. Where those workers completed base-scope work that would have been paid for on dayshift, explain whether the extra cost is the shift premium, additional supervision, extra mobilisation, or another supported component. Match plant invoices to the shifts that required an additional machine. Use the pricing basis the contract or instruction provides.

Check overlap with delay and daywork

Trace each disputed charge to a specific labour record, hire period or invoice. If a supervisor appears in both an acceleration build-up and a delay claim for the same shift, identify the work performed and allocate the supported amount once. If acceleration reduced the duration of other claimed costs, show the resulting period. Finish with a reconciliation from the payroll and plant records to the acceleration line in the served payment claim.

Worked example — measuring the extra shift

Suppose a New South Wales contractor originally planned six fitters on day shift to install a conveyor line. Access is delivered late. The contract administrator then directs an evening shift to preserve the commissioning date and confirms that reasonable additional shift costs will be paid. The contractor's payment claim includes the whole evening payroll. The respondent says it already pays for installation through the lump sum. Both positions need to be tested against the original resource plan and the actual direction.

Assume four fitters worked five eight-hour evening shifts, giving 160 hours. Their ordinary cost was $60 an hour and the evening cost was $85. If those 160 hours simply replaced ordinary hours already priced for the same installation, the additional labour cost is $25 times 160, or $4,000. Suppose an additional supervisor genuinely had to attend for forty hours at $95, adding $3,800. An extra lighting hire invoice attributable solely to that shift adds $900. The identified increment is $8,700 before GST. A claim for the full evening labour of $13,600 plus supervision and lighting would count the ordinary $9,600 twice on those facts.

If the work instead required additional labour hours beyond the original installation allowance, establish why. Compare installed quantities and earned hours on the two shifts. A congested workface and additional handovers may have reduced productivity. Explain the mechanism and supply records for that work area. The difference between total project budget and total actual cost absorbs many other effects and cannot isolate the instruction on its own.

Connect the instruction to a progress payment

Section 9(a) of the Building and Construction Industry Security of Payment Act 1999 (NSW) looks to the contractual calculation of a progress payment. Section 10(1) governs valuation of construction work. Identify the power to direct acceleration, any agreed price and the documented method of valuation. A message demanding that the contractor comply with its original completion date can have a different effect from a direction to introduce a second shift at the principal's cost. Read the preceding extension request and the administrator's response together.

The example assumes a direction and an agreement about reasonable additional costs. In a real claim, record who had authority to issue the direction and whether the contract required written notice of the cost. Where the project team discussed several recovery options, identify the option actually selected. An estimate for a weekend crane and a night crew does not prove that both were deployed. Link the chosen measures to shift rosters, induction records, plant invoices and photographs of the workface.

Compare the programme with the resource record

Show the completion date expected before the direction, the target imposed and the activities that could be shortened. If commissioning could not start without an independent power connection, additional fitting crews may have had little effect on the controlling date. That issue belongs in the explanation even where invoices show real additional expense. State how the direction was implemented and how its effects were measured under the agreed payment provision.

Finish the cost schedule with credits for ordinary crew hours, unused hire allowances and amounts previously paid through variation items. Keep prolongation costs in a separate line and check whether any dates overlap with the accelerated shifts. A summary arranged by instruction, shift, cost category and exhibit gives the adjudicator a route from the decision to accelerate through to the net additional amount sought. It also makes a partial valuation possible if only the labour premium or the lighting hire is accepted.