Retention can sit in the accounts long after the final measurement has been agreed. In NSW, section 13(3)(b) of the Building and Construction Industry Security of Payment Act 1999 allows a payment claim to include money the respondent holds under the contract that the claimant says is due for release. The release clause and project records explain why the particular sum has fallen due. NSW Act, section 13
Identify the release event
Read the wording for each instalment. The trigger may refer to practical completion of the subcontract works, certification under the head contract, expiry of a specified period or completion of identified rectification. These events can occur on different dates. For a mechanical services package, a handover sheet for one plant room may establish completion of that room. Check what else the contractual release milestone covered and exhibit the record that establishes it.
Rebuild the retained balance
Start with the first certificate showing a retention deduction. Carry forward the actual amounts withheld, check the cap, and subtract each release or credit already allowed. Compare the certificate history with the remittances. A line entered as retention released in a certificate and money actually paid on that certificate are different entries in the reconciliation. Identify any unpaid certified amount separately so the same dollars do not appear twice.
Answer the reason for withholding
Put the respondent's reason beside the release provision. If a particular defect is said to prevent release, identify the defect record, close-out evidence and wording said to connect it to the retention. Show the opening balance, the instalment due, any release already received and the sum still claimed. This treatment concerns cash deducted from progress payments. A bank guarantee has different mechanics.
Worked example — two release dates and one ledger
Suppose a New South Wales subcontract permits cash retention up to $50,000 and provides for half to be released on certified practical completion. The balance is releasable after the defects period and satisfaction of the final release conditions. The contractor claims all $50,000 when the work is handed over. The respondent schedules nothing, saying that two minor defects remain. Neither figure can be assessed properly until the actual dates, certificate and wording have been identified.
Assume the ledger shows $48,000 actually retained. A signed certificate records practical completion of the whole subcontract. On the example terms the first release is half of the cash held, or $24,000. If $6,000 of that tranche has already been returned, the outstanding first release is $18,000. The second $24,000 remains subject to its own conditions. A cap of $50,000 is a maximum deduction, and using it as the opening balance would overstate the security actually held.
Read the certificate and identify the work it covers. Handover of a production line may be separate from practical completion of the whole subcontract. Conversely, the contract may expressly provide for staged release by separable portion. If the certificate relates to only one portion, trace the retention attributable to that portion and the formula applying to it. Show the calculation and explain why the particular certificate activates it.
The NSW payment claim provision
Section 13(3)(b) of the Building and Construction Industry Security of Payment Act 1999 (NSW) permits the claimed amount to include money held by the respondent under the contract that the claimant says is due for release. Identify the held amount and the event that makes it due. The provision supplies a mechanism for including the money in the claim. Whether the first or second tranche has become payable still depends on the relevant release terms and project facts.
Distinguish cash withheld from an unconditional bank guarantee. A ledger recording $48,000 in cumulative cash deductions supports a money claim. A security register listing a guarantee with the same face value describes an instrument. Obtain the actual ledger or the instrument before deciding what relief to seek. A cash claim based solely on the nominal value of a guarantee can misdescribe both what the respondent holds and the contractual obligation to be performed.
Check the defects relied on
Ask which release condition the respondent says the outstanding defects prevent. In the example the first release follows the completion certificate, while final release has separate conditions. Match each condition with the certificate, defects list, inspection records and any notices required. If the schedule asserts a separate right to apply retention against repair costs, identify the contractual power, the amount appropriated and the transaction date. The existence of a defects list gives no numerical answer to the amount actually held.
Reconcile deductions claim by claim. Show opening retention, current deductions, credits, releases and closing balance. Use the payment certificates and bank receipts together because a certificate directing release may precede actual payment. If the ledger allocates a payment against work and retention in one entry, obtain the remittance advice and explain the split. Check the tax treatment against the original claims so a release does not inadvertently charge GST twice.
Conclude with separate lines for the tranche claimed, the amount actually paid and the remaining security. Link each line to a clause, a dated event and a record of the money. This lets the adjudicator determine the first release even where the parties continue to disagree about completion of the final defects work.