When money arrives after service of the payment claim, preserve the claim exactly as it went to the respondent. The adjudicator needs to see the original demand and a separate account of what happened afterwards. Replacing the original total in the exhibit obscures both.
Find out what the transfer covers
Match the date and amount in the bank record with the respondent's remittance advice. Check the invoice number, claim period and listed deductions. A single transfer can cover two progress claims or include a supplier payment made on the contractor's account. If the remittance allocates the money, reproduce that allocation and identify any disagreement. If no allocation is recorded, show what can be matched and where the payment's destination remains disputed.
Reconcile the figures on the same basis
Start with the served amount. Show the scheduled amount separately, then enter payments actually received with their dates and references. A scheduled allowance is an assessment and may still be unpaid. A paid amount that already appears as a credit in a cumulative claim should not be deducted again. Check whether the payment and the figures in the submission include GST before calculating the balance.
Keep the record current
If the money arrives before filing, include the remittance and reconciliation with the application. If it arrives while the adjudication is underway, follow the applicable procedure and any directions about further communications and service. Identify the payment without altering the historical claim or schedule. Where interest is claimed, separate the period before payment from the balance afterwards and show the basis used. The adjudicator should be able to distinguish amounts still disputed from amounts agreed but unpaid.
Worked example — the bank transfer covers two claims
Suppose a New South Wales subcontractor serves payment claim 8 for $120,000 on a tax-inclusive basis. The respondent schedules $75,000 and later transfers $60,000. The contractor's accounts system shows a $60,000 credit against the customer. That customer has two active projects and a separate overdue invoice. Subtracting the entire transfer from claim 8 without checking the remittance may produce an incorrect balance.
Assume the remittance allocates $45,000 to claim 8 and $15,000 to the other project. Against claim 8 the scheduled but unpaid sum is $30,000. The claimed but unscheduled difference is $45,000. Together those two amounts make $75,000 outstanding against the original $120,000 claim, assuming no other adjustments. The customer-level balance and the claim-level balance answer different questions. Attach the remittance and the relevant bank line, with unrelated transaction information removed.
Suppose a second $10,000 arrives after the adjudication application is made, expressly allocated to claim 8. Preserve the original served claim, the schedule and the calculation used at lodgment. Record the new receipt with its date and explain its effect on the outstanding balance, which is now $65,000 on the same assumptions. A subsequent payment changes the outstanding sum. Replacing the original claim document with a revised invoice can make it difficult for a reader to identify what was actually served.
Separate scheduled debt from disputed value
Section 16(1) and (2) of the Building and Construction Industry Security of Payment Act 1999 (NSW) addresses non-payment of all or part of a scheduled amount by the due date where the section's requirements are met. Section 17(1)(a)(i) concerns a scheduled amount below the claimed amount, and section 17(1)(a)(ii) concerns failure to pay all or part of the scheduled amount by the due date. Identify which ground applies and calculate the relevant application deadline from the event prescribed for that ground. A later part payment should never be assumed to restart the clock.
Where an adjudication determination already exists, keep its amount separate from the original sum claimed. Section 25(2) and (3) deals with the affidavit of non-payment when filing an adjudication certificate, including the position where part has been paid. Check receipts again immediately before filing. If a part payment is allocated to interest or costs, retain the allocation evidence and identify the component to which it relates.
Resolve ambiguous remittances openly
A reference such as “progress payment” is insufficient where several claims have the same customer and similar amounts. Check contemporaneous correspondence, any payment certificate and both ledgers. Ask for the allocation and preserve the reply. If the allocation remains disputed, set out the two competing calculations. Identify which bank receipt is agreed, which matter the parties say it belongs to and what each position does to the amount outstanding.
Prepare a one-page reconciliation using claim number, project, scheduled amount, date due, receipt date and amount credited. Check whether figures include GST and whether retention or deductions have already reduced the gross figure. Do not subtract a retention again where the served claim was already net of that sum. A reviewer should be able to trace each receipt exactly once from bank to remittance to the relevant claim line.
The practical result is a narrower and more intelligible dispute. The adjudicator can see the value contested, the payment accepted, the date it was received and the balance sought. That remains possible even if a further transfer arrives between lodgment and determination.