A switchboard may be fabricated and ready for delivery months before it is connected. The supplier invoice establishes a purchase price. To support a progress payment for that switchboard, explain the payment milestone, identify the equipment and show the value reached at the claim date.
Check what the supply terms pay for
Read the agreed schedule. A milestone on successful factory testing asks a different factual question from a milestone on delivery to site or commissioning. Exhibit the approved test record, delivery docket or commissioning sheet that answers the relevant question. Where the contract separates manufacture, installation and testing, keep the three amounts visible so a completed fabrication milestone does not carry credit for installation still outstanding.
Identify the component and the valuation basis
Record the equipment tag, serial number, storage location and the receiving or inspection record. On a batch of similar switchboards, match the identifiers to the particular project. Section 10(2) of the NSW Act directs valuation of related goods and services under the contract. Where the contract makes no express provision, the statutory valuation considers the contract prices and rates, agreed price adjustments and estimated rectification costs for defective goods. For components to form part of the works, that statutory basis includes only those already owned, or to be owned on payment, by the party for whom the work is carried out. NSW Act, section 10(2)
Follow the component through later claims
Identify any deposit or earlier payment allocated to the same equipment. Show the amount then due and what remains against delivery, installation or testing. If the schedule says the component was intended for another project, answer that point with its tag, approved drawings and dispatch or storage record. A general photograph of a workshop floor rarely resolves an identification dispute.
Worked example — switchboards held off site
Suppose a New South Wales electrical subcontract allows a progress payment of 70% of the agreed equipment price once identified switchboards pass factory inspection, are insured and vest in the purchaser on payment. Four boards are priced at $30,000 each. The supplier invoices the subcontractor for all four. At the claim date two boards have passed factory inspection, one awaits testing and one has yet to be assembled. The claim seeks $84,000, being 70% of the entire equipment price.
Apply the contractual conditions board by board. Assume the two inspected boards are labelled with the project and serial number, the required insurance is in force and title can pass on payment. The supported milestone is 70% of $60,000, or $42,000 before GST. The remaining $42,000 in the claim depends on conditions still outstanding. If one inspected board is subject to a supplier's retention-of-title clause, obtain evidence of how the subcontractor can transfer the title promised before including that board in the calculation.
Photographs should show the serial plate and enough of the equipment to identify it. A photograph of four indistinguishable cabinets on a factory floor establishes little about which units are allocated to the job. Use the factory release, test certificate, delivery schedule and supplier acknowledgment to connect each serial number to the purchase order. Where the equipment can be substituted between projects, identify the arrangement preventing an already claimed board from being allocated elsewhere.
The valuation of goods in New South Wales
Section 10(2)(a) of the Building and Construction Industry Security of Payment Act 1999 (NSW) values related goods and services by the contractual terms. Section 10(2)(b) addresses valuation where the contract makes no express provision, including the ownership treatment of components intended to form part of the work. Under that fallback, identify whether those components have become, or on payment will become, the property of the party for whom the work is being performed. Use the applicable route consistently and address its conditions.
A supplier invoice can show purchase price and order date while leaving delivery, appropriation and title uncertain. Payment of the invoice can remove one obstacle without proving that the contractual inspection occurred. Conversely, a signed factory acceptance test can establish technical completion while saying nothing about title or insurance. Give each record the function it can actually support. If the contract also requires a vesting certificate in an agreed form, identify the signed document and reconcile its item references to the claim.
Prevent the same equipment being paid twice
Carry a running register from factory through delivery, installation and commissioning. Record the unique identifier, gross price, milestone earned, amount previously paid and amount claimed this month. When the two boards are subsequently installed, credit the manufacturing or off-site payment before claiming the next stage. If the contract prices installation labour separately, retain that distinction in the register so a change in labour value does not alter equipment already paid for.
Check limited deliveries carefully. A carrier's signed receipt for two crates proves receipt of those crates at the stated destination. Verify their contents against serialised packing lists and identify any missing accessories included in the equipment price. If the contract permits partial milestones, quantify the missing elements under its terms. If it calls for a complete unit, explain how the documented delivery satisfies that requirement. The resulting claim gives the adjudicator a verifiable answer for each board and a clear account of what must still happen before the balance is earned.