How to prove percentage complete on an industrial work package

“Mechanical works substantially complete” is difficult to value. When a payment schedule assigns a lower percentage to the package, the adjudicator needs to know what that percentage represents, how the contract measures progress and what had been achieved by the claim date.

Identify what earns payment

Start with the package description and agreed payment breakdown. Fabrication, delivery, installation, testing and commissioning may carry separate values. The contract may instead assign one price to a completed milestone. Establish which basis applies. Where payment depends on an acceptance test, identify the test, its result and the person responsible for acceptance. A delivery docket answers the question of arrival. It cannot establish that commissioning is complete.

Show the physical position at the claim date

Break the package into identifiable equipment or work areas. For each, connect the achieved stage to a dated record. An inspection release may establish fabrication, a goods receipt may establish delivery, and a signed test sheet may establish operation. Keep photographs tied to equipment tags and locations. If a later photograph is used, explain how the contemporaneous records establish the earlier position.

Test the percentage against the money

Where the contract permits proportional valuation, show the basis of the weighting. Counting installed items can distort progress when one large unit carries most of the package value. Apply the agreed values where available, identify any judgment used, and deduct the value previously allowed on the same basis. Show which stage the respondent accepts and which it disputes. The adjudicator can then determine the disputed increment without revaluing an entire plant from an unexplained percentage.

Worked example — installed is not commissioned

Suppose a Victorian industrial electrical subcontract gives a switchroom package a lump sum of $200,000. Its agreed breakdown assigns $80,000 to manufacture, $30,000 to delivery, $70,000 to installation and $20,000 to commissioning. At the claim date manufacture and delivery are complete. Of ten equally weighted installation circuits, seven have passed the agreed installation inspection. Commissioning has not started. The accounts team proposes claiming 90% because most of the labour budget has already been spent.

Apply the contractual weights to the evidence. Manufacture and delivery contribute $110,000. Seven of ten installation circuits contribute $49,000 on these assumptions. The cumulative value is $159,000, or 79.5% of the package. If previous payments attributable to this work total $115,000, the current increment is $44,000 before GST and any applicable retention. Ninety per cent would produce $180,000 cumulatively, a difference of $21,000 that the site records and agreed weights do not support.

Change one fact and the outcome changes. If the contract makes installation a single milestone earned only on acceptance of all ten circuits, seven signed inspection sheets establish substantial progress but do not satisfy that milestone. Conversely, a weight schedule agreed for progress assessment may permit partial credit within installation. Identify whether the breakdown is an agreed payment mechanism, a tender allocation or a reporting schedule used only at site meetings. Read the milestone conditions and any later agreement together.

Victorian valuation and the claim-date cut-off

Section 11(1)(a) of the Building and Construction Industry Security of Payment Act 2002 (Vic) directs valuation of construction work in accordance with the contract. Section 11(1)(b) identifies the considerations where there is no express provision on valuation. A cost report measuring spend against budget can help explain commercial performance. Before using it to prove a progress payment, show how the contract connects spending or physical completion to the price that has been earned.

Put the cut-off date on the inspection schedule. A test sheet countersigned three days later may record an inspection actually performed before the cut-off. Ask the inspector to distinguish inspection date from signature date and attach the original record. An inspection first carried out after the cut-off raises a different question. Its later success cannot simply be inserted as an earned milestone at the earlier date. Keep a separate column for work confirmed in the following period.

Account for the uneven work

Equal weighting is convenient in the example but ten real circuits may require different equipment and labour. One high-voltage feeder may represent more installation value than several lighting circuits. Seek the pricing breakdown used when the parties agreed their weights. Where the breakdown is silent, describe the technical differences and identify the basis for any allocation. A weighted estimate should show quantities, assumptions and the calculation, with an alternative if one weight is contested.

Finally reconcile the package with the whole payment claim. Show cumulative value, deductions already applied and the increment now sought. Check that equipment claimed in the manufacturing stage has not reappeared as a separate materials-on-site item. Tie any changes in contract sum to an instructed variation and update the denominator consistently. Otherwise a package may appear to move backwards in percentage terms solely because its scope increased. A short note showing both the original and revised denominator lets the adjudicator distinguish new work from a genuine change in completion.

Where commissioning has several stages, mark the agreed release point for each. A successful continuity test, energisation permit and client acceptance certificate record different events. The payment assessment should name the event actually required for this package and the record showing that it occurred.

Read the Victorian Act