Proposal preparedOutcome: We helped the contractor prepare an acceleration offer of approximately $1.04 million.
Act and time limits
The NT engagement produced an acceleration offer. Its preparation did not start an adjudication period. For a subsequent payment dispute in the Territory, the Act sets the following timetable.
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)
- For a payment dispute under Part 3, prepare and serve the application on the other contracting parties and the appropriate adjudicator or prescribed appointer within 65 working days after the dispute arises. The count starts the next day.
- Identify the dispute under s 8 from the claim, the contract and the payment or rejection record. A qualifying high-value contract may provide a different adjudication process under s 10A.

For a remote Northern Territory project in September 2021, we helped the contractor prepare an acceleration offer. The task was to explain how the proposed earlier delivery could be achieved and what it would cost.
Turning the target into a proposal
We set out the acceleration schedule, the implementation plan and the deliverables. The financial proposal addressed incentives for extended site swings, completion incentives and wage increases.
We also assessed how the proposed changes would affect productivity. Adding hours or people to a remote site affects both cost and the programme; those effects needed to be considered together in preparing the offer.
The outcome
The offer priced the proposed acceleration at approximately $1.04 million and set out the instalments.
What the preparation demonstrates
An acceleration proposal should make the requested change understandable: the programme being changed, the proposed resources, the delivery commitments and the price. Connecting those elements gives the parties a concrete proposal to assess and a clearer record of what any later agreement covers.