Adjudication outcomeOutcome: We helped prepare the contractor’s suspension claim. The adjudicator valued suspension costs at $186,900.85 including GST, accepted the extension of time and rejected liquidated damages.
Act and time limits
For a current payment claim, select the project location to see the filing period.
Queensland
Building Industry Fairness (Security of Payment) Act 2017 (Qld) · ss 76 and 79(2)(b)
- Lower scheduled amount. Apply within 30 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 20 business days after the payment due date.
- No schedule and the claim was not paid in full. Apply within 30 business days after the later of the payment due date and the last day for giving a schedule. The schedule period is 15 business days after the respondent receives the claim, or the shorter period in the contract.
New South Wales
Building and Construction Industry Security of Payment Act 1999 (NSW) · s 17(2), (3)(c)–(e)
- Lower scheduled amount. Apply within 10 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 20 business days after the payment due date.
- No schedule and the claim was not paid in full. Serve the notice of intention to apply within 20 business days after the payment due date. Allow 5 business days after the respondent receives the notice to provide a schedule, then apply within 10 business days after that period ends.
Victoria
Building and Construction Industry Security of Payment Act 2002 (Vic) · s 18(2), (3)(c)–(e)
- Lower scheduled amount. Apply within 10 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 10 business days after the payment due date.
- No schedule and the claim was not paid in full. Give the notice of intention within 10 business days after the payment due date. Allow 5 business days from receipt for a schedule, then lodge within 5 business days after that period ends.
- These periods are for payment claims under the amended scheme from 15 April 2026. Earlier claims can fall under the transitional rules.
Western Australia
Building and Construction Industry (Security of Payment) Act 2021 (WA) · s 28(1)–(4)
- Contracts entered into on or after 1 August 2022. Apply within 20 business days after first becoming entitled to apply. A schedule for less than the amount claimed and failure to pay by the due date are distinct triggers.
- No schedule and payment is overdue. Give written notice of intention within 20 business days after the payment due date. Allow 5 business days from receipt for a schedule before using the no-schedule route.
- For contracts entered into before 1 August 2022, the Construction Contracts (Former Provisions) Act 2004 (WA), s 26(1), ordinarily requires an application within 90 business days after the payment dispute arises.
Northern Territory
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)
- For a payment dispute under Part 3, prepare and serve the application on the other contracting parties and the appropriate adjudicator or prescribed appointer within 65 working days after the dispute arises. The count starts the next day.
- Identify the dispute under s 8 from the claim, the contract and the payment or rejection record. A qualifying high-value contract may provide a different adjudication process under s 10A.

A construction suspension produced two connected disputes: the contractor's entitlement to the costs of suspension and the respondent's claim for liquidated damages. We helped prepare the contractor’s claim. The adjudicator gave the decision in September 2021.
The claim and its supporting record
We brought together payment claim 11, the adjudication application, a chronology, delay analysis and a detailed cost breakdown. That combination addressed the event, its time consequences and the amount claimed.
The reported decision
The adjudicator assessed the suspension costs under clause 34.4 of that contract. The respondent had disputed entitlement but had not challenged the quantum. The adjudicator compared the claimed costs with the contract and valued the relevant work at $186,900.85 including GST.
The adjudicator also accepted the contractor's entitlement to an extension of time. In that decision, the respondent's liquidated damages claim consequently failed.
What the preparation demonstrates
A delay claim needs an explanation of time as well as money. The chronology and programme analysis explain the extension sought; the breakdown and source records explain the costs. Presenting those components together also allows a response to liquidated damages to address the same events coherently.