Using a payment withholding request during NSW adjudication

A subcontractor awaiting a NSW adjudication decision may have an opportunity to preserve money further up the same contracting chain. The starting point is an adjudication application already made for the payment claim. A reduced payment schedule by itself does not activate this procedure.

Identify who owes the respondent money

Under section 26A, the claimant can serve the approved payment withholding request on the principal contractor for that claim. The statutory relationship turns on who owes, or will owe, the respondent money for work or materials connected with the work the respondent engaged the claimant to perform or supply. Trace that relationship from the project documents. A company identified as the developer on a site sign may be a different entity from the company that engaged the respondent. NSW Act, section 26A(1)–(4)

Prepare the request against the filed claim

Use the approved form and include the claimant's statutory declaration of genuine belief that the respondent owes the amount claimed. Match the parties, claim details and amount to the application and retain evidence of service. The principal contractor's retention obligation is limited to qualifying money payable to the respondent. It may be less than the amount claimed. Service of the request does not transfer the retained money to the claimant. NSW Act, section 26B(1)–(2)

Track the application through to determination

A part payment reduces the amount that must be retained. When the determination is served on the claimant, the claimant must serve a copy on the principal contractor within five business days. Record both service dates. Section 26B(3) specifies which events end the obligation, including the expiry of 20 business days after service of the determination on the principal contractor if an earlier ending event has not occurred. If the application is withdrawn, section 26D(3) requires the claimant to give the principal contractor written notice within five business days after withdrawal. NSW Act, section 26B(3)–(5) NSW Act, section 26D(3)

Worked example — a subcontractor one tier below the head contractor

Suppose a New South Wales electrical sub-subcontractor applies for adjudication of a $90,000 payment claim against the electrical contractor that engaged it. The head contractor owes the electrical contractor $55,000 for the relevant work. Another $40,000 will become payable under the same package. The developer separately owes the head contractor money under its head contract. Draw the three contractual relationships before preparing the approved request.

On these assumptions the relevant upstream payer is the head contractor owing money to the respondent electrical contractor. Sections 26A(1)–(4) and 26B(1)–(2) of the Building and Construction Industry Security of Payment Act 1999 (NSW) connect the request and retention obligation to the defined relationship and qualifying money. The amount already payable is $55,000. If the further $40,000 becomes payable while the obligation continues, the extra amount needed to cover the unchanged $90,000 claim is $35,000. The example assumes that the money relates to the relevant work and that no earlier ending event occurs.

Now suppose the respondent makes a $20,000 part payment after the initial $55,000 has been withheld. Under section 26B(4) the retention obligation reduces to the extent of that payment. The outstanding amount to be covered becomes $70,000 on these facts. Only another $15,000 would then be needed from later qualifying money. Record the receipt, its allocation and the amount already retained. The arithmetic concerns how much must be kept upstream, not an immediate right to draw $70,000 from the head contractor.

Get the declaration and the recipient right

Identify the exact respondent in the adjudication application and the legal entity owing money to it. Check contract names against purchase orders and progress certificates. A principal contractor may have a different legal name from the project delivery brand. Use the approved form and attach the required statutory declaration of genuine belief under section 26A(3). Check the claim number, the amount and the application details across the declaration and request before service.

Create a record of service on the upstream recipient, including the complete document, time, destination and method used. Keep the request separate from ordinary correspondence asking the developer to help obtain payment. A general request for assistance does not tell the recipient that the statutory mechanism has been invoked or identify the amount to which it applies. If the selected recipient disputes that it owes the respondent qualifying money, examine the contracting documents before assuming another group company is liable.

Keep track of what ends the obligation

Section 26B(3) identifies the events that end retention. These include payment of the claim and particular events involving withdrawal, failure to determine, a notice under the Contractors Debts Act 1997, or expiry of the stated period after service of the determination. Read the applicable paragraph and any qualification concerning a new application. The filing date of the original application on its own cannot supply a single expiry date for all those events.

Under section 26B(5), serve the determination on the principal contractor within five business days after it is served on the claimant. Record both service events separately and calculate the twenty-business-day period in section 26B(3)(d) from service on the principal contractor. If the application is withdrawn, check the separate notice obligation in section 26D(3). Keep the status of the adjudication and the notice history together so that the person managing recovery can identify which duty is current.

Record any direct payment, new qualifying amount or event ending retention as it occurs. The resulting timeline shows the sum originally claimed, the amount that could be retained at each stage and the point at which the obligation ceased. It also avoids presenting money held by another party as money already received by the claimant.