A signed docket can be persuasive evidence of who was on site and what equipment was used. Its meaning depends on the wording beside the signature, the signatory’s role and the daywork terms. Build the claim around those facts before multiplying hours by a rate.
Read the instruction and the signature together
Identify the work requested and how it differed from the original scope. Find the direction to proceed on daywork, if one was given. Read the docket acknowledgment closely. A foreman might confirm the hours or observe the work while leaving the price for the contract administrator. If the other party accepts the attendance but disputes the instruction, a submission that merely repeats the hours misses the issue.
Rebuild the charge from the site records
Match the docket to the date, location, crew and plant. For a crane lift, check whether the crane rate includes the operator. Compare the docket hours with the hire invoice and the agreed treatment of travel, minimum hire and standby. For labour, apply the classification that matches the person and the task. Identify any supervision or overhead already included in a rate before applying a separate allowance.
Deal with unsigned or amended dockets
Keep the first version, any correction and the record showing who received each. On an unsigned day, a supervisor’s diary, access log, plant record or contemporaneous email may corroborate attendance. State exactly what each record establishes. Then address any contractual requirement for submission or approval of the docket. Present the days separately so a disagreement about one shift does not obscure the supported work on the others.
Worked example — an operator counted twice
Assume an industrial subcontract in Western Australia provides for instructed daywork. The signed schedule prices an excavator with its operator at $190 an hour, a spotter at $75 an hour and a labourer at $65 an hour. On Tuesday the superintendent directs the crew to uncover a buried crossing. The foreman signs a docket recording six hours for the excavator, six for the operator, six for the spotter and four for the labourer. The signature box confirms attendance and the times recorded.
If the claim treats the operator as a second labour charge at $65 an hour, it produces $2,240. Applying the inclusive plant rate gives $1,140 for the machine and operator, $450 for the spotter and $260 for the labourer. The supported total is $1,850 before GST. The $390 difference has a precise cause. The operator really attended for six hours, and the docket correctly identifies that person. The error arises when a record of attendance is converted into a second priced line.
Now suppose the schedule allows only four hours for the spotter. The contractor can identify the scheduled quantity and show the extra two hours alongside the supervisor's diary recording the time the excavation remained open. Compare the diary with the traffic-control requirement for that crossing. If the spotter went to another crew for the final two hours, split the docket at the transfer. A person can be present on the project throughout the shift while being chargeable to this instruction for only part of it.
Which valuation rule applies?
For a contract governed by the Building and Construction Industry (Security of Payment) Act 2021 (WA), section 19(1)(a) directs the valuation of construction work by the contract where it provides for the matter. Section 19(1)(b) identifies the matters to consider in the absence of a contractual valuation provision. Locate the agreed daywork schedule and any provisions covering minimum hire, breaks and travel before resorting to a supplier invoice. Establish which Western Australian statutory regime applies to the contract before relying on this provision.
A hire company's invoice may show a ten-hour minimum although the principal agreed to pay only hours worked. That invoice explains an expense the subcontractor incurred. To recover the minimum, identify the provision or separate instruction passing that expense through. Conversely, an agreed all-inclusive day rate might apply even though the machine spent an hour waiting for access. Quote the governing words and explain how the time records satisfy them.
Reconcile the instruction with the claim
Prepare one line for each person or plant item and record the shift, instruction number, chargeable hours, inclusive rate and extension. Give each original docket a stable reference. Where the office later corrected a classification, show the foreman's original entry and describe why the correction follows from the rate sheet. Never silently replace a signed page with the corrected summary.
Ask the reviewer to reproduce the total using only the instruction, docket and rates. Next ask them to identify any work already paid under the lump sum or an earlier variation. On this example that means checking whether exposing the crossing was already included in the agreed excavation item. Where only extra hand digging was instructed, split the changed activity from the ordinary machine excavation. The adjudicator can then see exactly which time, price and scope are disputed and can adjust one shift without recosting the entire package.
Record the docket number on the payment claim as well as the daywork register. If two subcontractors used the same excavator on the same date, identify the start and finish times for each instruction and obtain the hire allocation before charging the machine to either job.