Proving excavation quantities in adjudication

An excavator operator, a surveyor and a truck driver can give different figures for the same cut. The operator sees the ground disturbed, the surveyor measures the space between surfaces, and a truck docket records material loaded or transported. The adjudication application needs the quantity calculated on the basis the contract pays for.

Establish the measurement limits

Read the pay item, specification, drawings and instructions for the disputed area. Identify the starting surface, finished profile, lateral limits and any allowance for working space. If stripping is paid separately, establish which surface becomes the starting point for bulk excavation. Queensland Transport and Main Roads publishes a separate measurement specification for general earthworks. Where the contract incorporates MRS04, use the edition and amendments identified in that contract. TMR roadworks specifications, MRS04 General Earthworks

Make the survey calculation reproducible

Identify the two surveys by date, coordinate system and vertical datum. Mark the disputed area on a plan. If one survey stops short of the boundary or a surface has been interpolated, show where and how that affects the result. Provide representative cross-sections and the volume calculation. A coloured model on its own gives the reader no reliable way to locate the difference between the parties’ figures.

Explain where the quantities diverge

Compare the respondent’s measurement with yours over the same footprint. Then isolate the difference. It may be a changed excavation limit, an additional instructed cut, or stripping included in both quantities. Use truck records or disposal receipts to corroborate removal where relevant. If they record loose volume or weight, explain any conversion before using them to support an in-ground quantity. Finish with the payable quantity, the applicable rate and the amount already recognised for that item.

Worked example — measuring in situ excavation

Assume a Queensland subcontract prices bulk excavation at $42 per cubic metre measured between agreed ground surfaces. The joint pre-start survey and the claim-date survey give 1,240 cubic metres inside the approved boundary. Truck tickets total 1,520 cubic metres of loose spoil. The contractor's original worksheet used the tickets and extended them to $63,840. The respondent's schedule allows 1,100 cubic metres, or $46,200. There are three measurements and each answers a different question.

Start with the contractual unit. Spoil expands when disturbed and truck capacity describes a load after excavation. The difference between loose and in situ volume cannot by itself establish underpayment. Using the joint surfaces gives $52,080 before GST. Against the scheduled valuation the difference is $5,880. The difference against the worksheet is $11,760. Identify both adjustments so the reader can see how the figure now supported relates to the amount actually claimed.

Test the disputed strip

Suppose the 140 cubic metres omitted from the scheduled measurement lies along the eastern boundary. Ask for the boundary used by each surveyor. Overlay the polygons on the same coordinates, mark the strip and print a cross-section through it with the pre-start surface and final surface labelled. Read the excavation instruction and drawing revision together. The survey can establish that material was removed. The instruction determines whether the strip lies within payable excavation or was overbreak for the subcontractor's account.

Inspect the date of the finishing survey. Material may have been backfilled before the surveyor arrived. Interim level shots can then matter, particularly for a trench covered as pipe installation advanced. Label measured points and interpolated points separately and show the spacing. Where a corner was inaccessible, explain the assumption and demonstrate its effect on the result. A reviewer should be able to change that assumption without rebuilding every other area.

Queensland's valuation provision

Section 72(1)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) uses the contractual valuation method where the contract provides one. Section 72(1)(b) identifies valuation considerations where it does not. For the example the agreed surfaces and boundary define how the item is measured. A general reference to prevailing earthworks prices cannot resolve a disagreement about which surface or boundary the contract adopts.

Review any separate items for rock, haulage and disposal. A single excavation can support several differently defined operations, but a wet tonne on a disposal invoice cannot be added directly to a cubic metre of excavation. A conversion needs a defensible density and a reason why the contract permits its use. If the excavation rate includes offsite disposal, show where a separate disposal charge has been removed. Check also whether an allowance for unsuitable material uses a different boundary from the formation excavation.

Make the measurement usable on paper

Attach a plan readable at normal page size, the two surface dates, the calculation report and a schedule by zone. Include the coordinate system, vertical datum and the method used for the volume comparison. Retain the underlying survey files so another surveyor can reproduce the calculation. A screenshot of the software's total without those inputs gives the respondent little opportunity to identify the precise disagreement.

Conclude the item with the gross valuation, previous payments against that quantity and the current balance. If the respondent accepts one zone, identify it separately and concentrate the explanation on the disputed strip. That leaves a clear measurement outcome even if the adjudicator adopts a different treatment of the boundary.