Entitlements reviewedOutcome: We identified a misunderstanding about which rate band applied to the work under the panel agreement.
Act and time limits
This engagement reviewed the panel agreement’s pricing method. For a statutory payment dispute, select the location of the work.
Queensland
Building Industry Fairness (Security of Payment) Act 2017 (Qld) · ss 76 and 79(2)(b)
- Lower scheduled amount. Apply within 30 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 20 business days after the payment due date.
- No schedule and the claim was not paid in full. Apply within 30 business days after the later of the payment due date and the last day for giving a schedule. The schedule period is 15 business days after the respondent receives the claim, or the shorter period in the contract.
New South Wales
Building and Construction Industry Security of Payment Act 1999 (NSW) · s 17(2), (3)(c)–(e)
- Lower scheduled amount. Apply within 10 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 20 business days after the payment due date.
- No schedule and the claim was not paid in full. Serve the notice of intention to apply within 20 business days after the payment due date. Allow 5 business days after the respondent receives the notice to provide a schedule, then apply within 10 business days after that period ends.
Victoria
Building and Construction Industry Security of Payment Act 2002 (Vic) · s 18(2), (3)(c)–(e)
- Lower scheduled amount. Apply within 10 business days after receiving the payment schedule.
- Scheduled amount unpaid. Apply within 10 business days after the payment due date.
- No schedule and the claim was not paid in full. Give the notice of intention within 10 business days after the payment due date. Allow 5 business days from receipt for a schedule, then lodge within 5 business days after that period ends.
- These periods are for payment claims under the amended scheme from 15 April 2026. Earlier claims can fall under the transitional rules.
Western Australia
Building and Construction Industry (Security of Payment) Act 2021 (WA) · s 28(1)–(4)
- Contracts entered into on or after 1 August 2022. Apply within 20 business days after first becoming entitled to apply. A schedule for less than the amount claimed and failure to pay by the due date are distinct triggers.
- No schedule and payment is overdue. Give written notice of intention within 20 business days after the payment due date. Allow 5 business days from receipt for a schedule before using the no-schedule route.
- For contracts entered into before 1 August 2022, the Construction Contracts (Former Provisions) Act 2004 (WA), s 26(1), ordinarily requires an application within 90 business days after the payment dispute arises.
Northern Territory
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)
- For a payment dispute under Part 3, prepare and serve the application on the other contracting parties and the appropriate adjudicator or prescribed appointer within 65 working days after the dispute arises. The count starts the next day.
- Identify the dispute under s 8 from the claim, the contract and the payment or rejection record. A qualifying high-value contract may provide a different adjudication process under s 10A.

A company working under a panel agreement with a government organisation asked us to review its payment entitlements. We identified a misunderstanding about how the agreement’s banded rates determined the price.
The pricing issue
The engagement concerned the operation of the schedule, rather than simply checking the arithmetic of an invoice. To understand an amount payable under a banded system, the pricing method and the basis for selecting the applicable band must be understood together.
The outcome
We identified how to select the applicable rate band for the work charged under the agreement.
What the preparation demonstrates
For a similar review, we assemble the panel agreement, the complete rates schedule, the relevant work orders and the calculation used in each invoice. We work through a sample item from the instruction to the selected band and the resulting charge.
Explaining those steps exposes the precise disagreement. It also provides a useful structure for a payment submission: identify the contractual method, show the project inputs and then show how those inputs produce the claimed amount.
Explore related experience
Put the evidence to work.
Tell us about the project, the disputed amount and any approaching deadline.
Discuss your claim →