
Understand the work.
Roads, bridges and civil works. Scope changes, site conditions and the records behind the claim.
AdjudicateAdjudication, engineering and quantity surveying expertise for construction payment disputes.
Many payment claims need further work before they are ready for adjudication.
Costs are sometimes claimed under extension-of-time provisions that provide extra time but no right to compensation. The work or cost may instead support a variation or another contractual payment claim. We also identify instructions and changes to the work that may give rise to payment entitlements which have been overlooked.
Sometimes the better course is to take a step back and prepare the payment claim properly. We assess your contract, instructions, valuation and supporting records, then prepare a claim that puts you in the strongest possible position before adjudication.
After receiving the payment schedule, we review the reasons for withholding payment and prepare the adjudication application to pursue the disputed amount.
You’ve completed the work, but payment hasn’t followed. We review the contract, invoices and payment history, then explain your options.
Let’s look at your claimWe prepare payment claims and examine the reasons given for withholding payment. The contract, calculation and supporting evidence are brought together in one clear case.
Discuss your payment claimWe prepare claimant adjudication applications, written submissions and indexed evidence. Every disputed amount is tied to its contractual basis, calculation and supporting documents.
Discuss adjudicationWhen the dispute is about what was done or what it is worth, the technical detail matters. We examine scope, variations and valuation alongside the contract.
Talk through the disputeWe prepare extension of time claims supported by the contract, notices, programme analysis and project records. The submission connects each delay event to its effect on the completion date.
Discuss your extension of timeWe prepare acceleration proposals and claims, connecting the revised programme, additional resources and productivity effects to a clear cost calculation.
Discuss accelerationWe examine the completion date, extensions of time, delay evidence and the contractual basis for the amount claimed. We prepare a reasoned response to disputed liquidated damages.
Discuss liquidated damagesWe challenge disputed backcharges by examining the alleged work or loss, contractual entitlement, notices, records and calculation. Each deduction is addressed against the supporting evidence.
Discuss disputed backcharges
Roads, bridges and civil works. Scope changes, site conditions and the records behind the claim.

Buildings and mechanical, electrical and plumbing services. Drawings, quantities and contract requirements.

Energy and industrial projects. Technical issues explained through clear evidence and a checked valuation.
Every claim is assessed before we take it on. Send us the contract, the payment claim and the payment schedule. An experienced adjudicator will assess the strength of your claim and tell you whether it is worth pursuing. There is no charge for the assessment.
Our director is a Chartered Engineer, a Chartered Quantity Surveyor, Planner, Forensic Schedule Analyst, construction lawyer and a registered adjudicator. We can check the drawings, value the work and assess your entitlement under the contract in one in-house review. That keeps your fee down by reducing the need to brief separate specialists to work through the same records.
If we take your claim on, you receive a fixed quote in writing. You know the cost before you commit.
Your engagement with Adjudicate Now covers assessment and preparation of your payment claim or adjudication application. We do not act as your lawyers. Legal advice or representation requires a separate engagement.
No two claims cost the same. The fee reflects four things:
A well-documented claim may be adjudicated immediately. We will tell you in the assessment if anything is missing, how to close the gaps and if it needs resubmission in the next payment cycle or develop a recovery strategy if it is final.
Fees have ranged from $5,000 on a $50,000 claim to six figures on multi-million-dollar payment claims and adjudications prepared over weeks or months.
The adjudication application fee and the adjudicator's fees are charged by others and are not part of our quote.
Four featured examples are shown below. Explore the full collection of case studies.
View all case studies
We helped prepare the contractor’s suspension claim. The adjudicator valued suspension costs at $186,900.85 including GST, accepted the extension of time and rejected liquidated damages.
Read case studyFor a current payment claim, select the project location to see the filing period.
Building Industry Fairness (Security of Payment) Act 2017 (Qld) · ss 76 and 79(2)(b)
Building and Construction Industry Security of Payment Act 1999 (NSW) · s 17(2), (3)(c)–(e)
Building and Construction Industry Security of Payment Act 2002 (Vic) · s 18(2), (3)(c)–(e)
Building and Construction Industry (Security of Payment) Act 2021 (WA) · s 28(1)–(4)
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)

We found the subcontractor’s notice from the day the pipe was discovered. The subcontractor received payment for the disputed variation.
Read case studyThe contract required notice within seven days. The subcontractor emailed on the day it found the pipe. For a statutory claim on your project, select its location below.
Building Industry Fairness (Security of Payment) Act 2017 (Qld) · ss 76 and 79(2)(b)
Building and Construction Industry Security of Payment Act 1999 (NSW) · s 17(2), (3)(c)–(e)
Building and Construction Industry Security of Payment Act 2002 (Vic) · s 18(2), (3)(c)–(e)
Building and Construction Industry (Security of Payment) Act 2021 (WA) · s 28(1)–(4)
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)

We identified which pricing document took priority. The subcontractor recovered the cost of all eight detours, including the two beyond its tender allowance.
Read case studyRecovery turned on the priority of the schedule of rates. For a statutory claim, select the location of your project.
Building Industry Fairness (Security of Payment) Act 2017 (Qld) · ss 76 and 79(2)(b)
Building and Construction Industry Security of Payment Act 1999 (NSW) · s 17(2), (3)(c)–(e)
Building and Construction Industry Security of Payment Act 2002 (Vic) · s 18(2), (3)(c)–(e)
Building and Construction Industry (Security of Payment) Act 2021 (WA) · s 28(1)–(4)
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)

We helped the contractor prepare an acceleration offer of approximately $1.04 million.
Read case studyThe NT engagement produced an acceleration offer. Its preparation did not start an adjudication period. For a subsequent payment dispute in the Territory, the Act sets the following timetable.
Construction Contracts (Security of Payments) Act 2004 (NT) · ss 8, 10A and 28(1), (3)
Tell us where your project is located. We review your contract, payment documents and service dates before recommending the next step.
Who owes you, what work you did, and when payment was due. We start with the essentials.
We review the key documents and explain the available paths, likely costs and next steps.
Once you agree the scope and fees, we help you take the next step towards payment.

A construction payment dispute is about more than an unpaid invoice. It can turn on scope, quantities, variations and the work actually delivered.
Albert Merolla is a registered Queensland adjudicator, Chartered Engineer and Chartered Quantity Surveyor. He brings the contract, programme, site records and valuation together in your submission.
About Albert MerollaStart with your contract or purchase order, the unpaid invoices, any payment claim or response, and the key emails. If something is missing, tell us what you have.
The initial assessment is free. If we take your claim on, we give you a fixed quote in writing before you commit. See what the fee depends on.
Email [email protected] with the project location and the relevant dates. Put any approaching deadline in the subject line. Sending an enquiry does not confirm that we are acting for you.
We prepare claims and applications for clients. Our preparation service is separate from the independent adjudicator appointed to determine your application. We do not operate as an adjudication bureau.
Adjudication Lawyers Pty Ltd trading as Adjudicate Now. Contact us to arrange a meeting.
All locations →Tell us a little about the payment issue.
We’ll take it from there.